MONROE COUNTY

MONROE COUNTY

BRIGHTON 260101
GATES CHILI 260401
GREECE 260501
E. IRONDEQUOIT 260801
W. IRONDEQUOIT 260803
HONEOYE FALLS 260901
SPENCERPORT 261001
HILTON 261101
PENFIELD 261201
FAIRPORT 261301
EAST ROCHESTER 261313
PITTSFORD 261401
CHURCHVILLE CH 261501
ROCHESTER 261600
RUSH HENRIETTA 261701
BROCKPORT 261801
WEBSTER 261901
WHEATLAND CHIL 262001
MONROE 1 BOCES 269100
MONROE 2 BOCES 269200
















Overdue Final Cost Reports

Final Cost Reports Due No Later than June 30, 2008

THE STATE EDUCATION DEPARTMENT

FACILITIES PLANNING


UPDATED: 11/20/09 at 17:38:22




BRIGHTON CENTRAL SCHOOL DISTRICT FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-01-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GATES CHILI CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-04-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




GREECE CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-05-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           Autumn Lane Elementary:
00-1735    Additions and Alterations    0-009-009  10/24/01   02 - 16                4,694,339    4,737,423   01/23/09    AJP     01/23/09   06/25/08    09/16/08  MGL

           English Village Elementary:
00-1736    Additions and Alterations    0-010-013  10/24/01   02 - 16                4,233,664    4,266,581   01/23/09    AJP     01/23/09   06/25/08    09/16/08  MGL

           Athena Middle/High School:
01-0912    Additions and Alterations    0-017-025  12/13/02   02 - 16               28,716,127   29,002,633   01/23/09    AJP     01/23/09   06/25/08    08/31/09  MGL


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




EAST IRONDEQUOIT CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-08-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WEST IRONDEQUOIT CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-08-03-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           Irondequoit High School:
06-0065SC  Visual Structural Inspection 0-001-SC5  08/07/06   16                             0       12,663     /  /                /  /       /  /      04/06/06  JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HONEOYE FALLS - LIMA CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-09-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




SPENCERPORT CENTRAL SCHOOL DISTRICT FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-10-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           New Press Box:
01-0288    New Construction             7-016-001  09/21/01   02 - 16                        0       23,500     /  /                /  /       /  /      11/01/06  MGL

           Concession/Ticket:
04-0401    New Construction             7-017-001  04/29/05   02 - 16                        0       28,000     /  /                /  /       /  /      02/15/06  RDR

           Soccer Toilets:
04-0402    New Construction             7-018-001  04/29/05   02 - 16                        0       11,200     /  /                /  /       /  /      02/15/06  RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




HILTON CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-11-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PENFIELD CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-12-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PENFIELD CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-12-11-19
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




FAIRPORT CENTRAL SCHOOL DISTRICT FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-13-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




EAST ROCHESTER UFSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-13-13-03
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




PITTSFORD CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-14-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           New Middle School:
06-0411SC  Visual Structural Inspection 0-025-SC1  11/03/06   16                             0       22,050     /  /                /  /       /  /      05/15/06  JOD

           Bus Garage:
03-0128    Reconstruction               5-011-067  08/13/04   16                        36,360       36,360   04/21/09    AJP     04/21/09   02/19/09    10/10/06  JOD


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




CHURCHVILLE CHILI CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-15-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           Concession (metal bldg.):
03-1685    New Construction             7-011-001  04/26/05   02 - 16                        0       29,000     /  /                /  /       /  /      09/06/06  RDR

           Pressbox:
03-1687    New Construction             7-014-001  04/26/05   02 - 16                        0       13,750     /  /                /  /       /  /      09/06/06  RDR


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




ROCHESTER CITY SCHOOLS FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-16-00-01
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




RUSH HENRIETTA CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-17-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BROCKPORT CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-18-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WEBSTER CENTRAL SCHOOL DISTRICT FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-19-01-06
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




WHEATLAND CHILI CSD FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-20-01-04
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BOCES MONROE #1 FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-91-00-00
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition




BOCES MONROE II-ORLEANS FINAL COST REPORTS DUE JUNE 30, 2008 FOR CAPITAL PROJECTS
District No.: 26-92-00-00
last updated on 11/20/09
REVIEW     BUILDING NAME/               BLDG./     NYSED                            FINAL        ESTIMATED    FCR       FCR       FCR TO     FCR TO      SUBST.    PRJ.
NUMBER     PROJECT SCOPE                PROJ. NO.  APPROVAL   CSI CODES             COST         COST         APPROVED  REVIEWER  STATE AID  PROJ. MGR.  COMPLETE  MGR.
______________________________________________________________________________________________________________________________________________________________________

           NO FINAL COST REPORTS DUE:
  -        FOR THIS DISTRICT                         /  /                                    0            0     /  /                /  /       /  /        /  /       


CSI Codes: 02-Site  02-Asbestos  04-Masonry  07-Roof  08-Doors/Windows  09-Finishes  10-Specialties  13-Special Const  14-Elevator
           155-HVAC  15-Plumbing  16-Electric  02-16 New/Addition