BINGHAMTON 030200
BROOME BOCES 039000
CHENANGO FORKS 030101
CHENANGO VALLE 030701
DEPOSIT 031301
HARPURSVILLE 030501
JOHNSON CITY 031502
MAINE ENDWELL 031101
SOUTH MOUNTAIN 030201
SUSQUEHANNA VA 030601
UNION-ENDICOTT 031501
VESTAL 031601
WHITNEY POINT 031401
WINDSOR 031701
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
Benjamin Franklin School:
02-1719 Reconstruction 0-008-009 12/08/03 4,9,155,15,16 3,439,285 3,439,285 09/08/09 AJP 09/08/09 10/19/07 08/30/05 HCM
Woodrow Wilson:
02-1721 Reconstruction 0-016-013 12/08/03 2,8,9,155,15,16 3,067,820 3,067,820 08/25/08 AJP 08/25/08 08/16/07 12/01/05 HCM
Thomas Jefferson Elem.:
02-1722 Reconstruction 0-019-004 12/08/03 4,7,8,9,155,15,16 2,131,472 2,131,472 08/25/08 AJP 08/25/08 10/19/07 03/30/05 HCM
Horace Mann School:
99-1373 Reconstruction 0-022-008 04/19/00 7 148,117 148,117 05/22/03 GJY 05/22/03 05/16/03 09/10/02 BJB
02-1723 Reconstruction 0-022-009 12/08/03 2,8,9,155,15,16 908,911 908,911 / / / / 10/19/07 03/30/05 HCM
02-1638 Reconstruction 0-022-010 03/21/03 2,7 545,083 545,083 08/06/08 AJP 08/06/08 10/19/07 01/05/05 HCM
Security Booth #1 @ HS:
03-1614 New Construction 7-035-001 07/16/04 02 - 16 7,758 7,758 01/13/09 AJP 01/13/09 10/19/07 09/03/04 HCM
Security Booth #2 @ HS:
03-1615 New Construction 7-036-001 07/16/04 02 - 16 7,758 7,758 08/04/08 AJP 08/04/08 10/19/07 09/03/04 HCM
Security Booth #3 @ HS:
03-1616 New Construction 7-037-001 07/16/04 02 - 16 7,759 7,759 08/18/08 AJP 08/18/08 10/19/07 09/03/04 HCM
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition
REVIEW BUILDING NAME/ BLDG./ NYSED FINAL ESTIMATED FCR FCR FCR TO FCR TO SUBST. PRJ.
NUMBER PROJECT SCOPE PROJ. NO. APPROVAL CSI CODES COST COST APPROVED REVIEWER STATE AID PROJ. MGR. COMPLETE MGR.
______________________________________________________________________________________________________________________________________________________________________
NO FINAL COST REPORTS DUE:
- FOR THIS DISTRICT / / 0 0 / / / / / / / /
CSI Codes: 02-Site 02-Asbestos 04-Masonry 07-Roof 08-Doors/Windows 09-Finishes 10-Specialties 13-Special Const 14-Elevator
155-HVAC 15-Plumbing 16-Electric 02-16 New/Addition